Housing Campus for the US Army

Fort Bliss has recently gone through an unprecedented expansion that included 24 two-story buildings for Unaccompanied Enlisted Personnel Housing totaling over one million square feet of space. The project was delivered by the design-build team headed by Sundt Construction. In close coordination with architect Michael Baker Jr. Incorporated and electrical engineers at the RMH Group, Bergelectric professionals provided design-assist services for all electrical and lighting, including motion sensors, branch wiring, electrical distribution and 500kVA primary transformers.

From materials deliveries to daily flow of more than 100 Berg electricians through the Fort Bliss entrance gate, security was of utmost importance at this military installation. Recognizing that personal vehicles are not allowed on site, and avoiding back-ups at the only security gate through which over 1,000 employees had to enter, Bergelectric bused crews onto the base and staggered start times to improve efficiency on this $172-million project.

Size
1 Million-square feet

Electrical Construction Cost
$29.7 Million

Duration
April 2009 – January 2012

Delivery Method
Design Build

Other Team Members
Sundt Construction, Inc.
US Army Corps of Engineers
The RMH Group

Berg Regional Office
Austin